Two Additional Club Hangars

Finally after years of negotiation with Council, we can now proceed with the construction of hangars 9 & 10. Land clearing commenced yesterday 23rd October. About half of the required clearance was achieved with the remainder scheduled for next weekend (weather permitting). A photo of the first day’s progress is attached.